Structure Evaluation Engineers, Inc.
(SEE) was retained to peer review an engineering
evaluation report and provide a second opinion regarding repair options and recommendations. The
parking garage is relatively a new three-level precast parking garage
with pre-topped double-T decks. It provides approximately 330 parking spaces
for customers. The problems associated with the garage included concrete delamination, failed
T-to-T joint sealants, failed expansion joints, differential elevation between adjacent double-T
flanges, and high chloride levels for both elevated
decks.
The original evaluation report indicated that some of the double-T flange
stainless steel connectors were failed along the welds. However, no explanation was given why
they failed. Review of the construction documents revealed that the design of the roof deck was
changed during the construction to allow emergency fire trucks over the roof deck.
SEE found out that the same
standard passenger-car flange connectors were specified and used for both roof and
intermediate levels. We recommended contacting the original contractor to repair the
connectors immediately and not to allow trucks over the roof until appropriate repairs are done. In
the meantime, the ownership approved to proceed with other repairs that included improvement of
surface drainage.
SEE provided
structural peer review and condition assessment, prepared the repaired bid
documents for the parking garage, assisted the owner with bidding the project, and
oversaw the construction.
|